Project: New Office.
Works Timescale: 8 weeks
BACKGROUND:
Birse Rail Ltd occupy a number of floors within Lyndon House, Birmingham.
During 2006 the decision was taken to occupy another floor to accommodate a team of Directors and staff in a modern working environment.
SERVICES PROVIDED:
Phase 1
McCarthy & Associates conducted a full survey and feasibility study of the existing building space was fully surveyed. A detailed cost proposal and timing plan was provided. McCarthy and Associates recommended project management services based on an “Open book” partnership approach.
Phase 2
As part of the project, McCarthy and Associates obtained building regulations approval using their “Lantac” partnership with Coventry City Council.
Once layouts and specification were agreed, the works programme began. The existing office was stripped out and refurbished, including upgraded M&E services, a new ceiling, lighting, decoration, carpets, kitchen area and curved glass partitioning.
McCarthy and Associates provided all of the furniture elements, including workstations, seating plus “Plug In” power and Data to each workstation.
Case Studies :
Tarmac | Warwick District Council | Space 4 | TNA Europe | Outokumpu
| Anglo Irish Bank | Birmingham International Airport |
Black Country Chamber of Commerce | BMI Health Services | Wolverhampton and Dudley Breweries | St Modwen Properties | Dunlop Aerospace | Coram Showers
| Golley Slater | Veolia Environmental
| Madani High School
|